The works on the much awaited MMTS ( Multi Modal Transport System)
phase -II project in the twin cities will commence very soon in this month
itself. The joint venture partners, who have been awarded this
prestigious project, have deposited the requisite Performance Guarantee amount
with M/s Rail Vikas Nigam Limited (RVNL) a few days back. With this, decks have
been cleared to launch the field works on this project.
Shri
P.K.Srivastava, General Manager/SCR conducted a high level review meeting at Rail
Nilayam today i.e. 14th July, 2014, on the progress of the
Railway projects taken up by RVNL on the Zone. Shri P.Srinivas, Chief Project
Manager/RVNL, Secunderabad briefed the General Manager on the present status
of various key Railway works under taken by RVNL.
on
this occasion, Shri Srivastava emphasized that there shall be no
further delay in commencing the work on MMTS phase-II as this project is
critical in strengthening the Railway infrastructure in twin cities. He
also stressed on close co-ordination between RVNL and the Divisional/Zonal
Railway authorities to ensure the works progress at a brisk pace for their
expeditious completion. The progress achieved vis-à-vis the set targets shall
be reviewed constantly at the highest levels, he directed the officials
involved in this project.
Major works under MMTS phase-II project include -
Sl.No
|
Section
|
Length
(in KMs)
|
Description of work
|
1
|
Sanathnagar – Moula Ali
|
22.4
|
Doubling and Electrification
|
2
|
Moula Ali – Ghatkesar
|
12.2
|
Quadrupling and Electrification
|
3
|
Moula Ali – Malkajgiri – Sitafalmandi
|
10
|
Doubling and Electrification
|
4
|
Secunderabad – Bolarum
|
14
|
Electrification and Remodeling of stations.
|
5
|
Bolarum – Medchal
|
14
|
Doubling and Electrification
|
6
|
Telapur – Patancheru
|
5.5
|
Restoration of Track and Electrification
|
7
|
Airport connectivity
Falaknuma FM)– Umdanagar (UR)- Shamshabad
(Rajiv Gandhi International Airport)
|
20
|
New line from Umdanagar to Airport
and doubling from Falaknuma – Umdanagar with Electrification.
|
The
present estimated cost of this project is Rs.817 crs, out of which 2/3rd
of the cost will be borne by the State Government. Except the works in
Falaknuma-Umdanagar-Shamshabad (Airport connectivity) stretch, for
which tenders are yet to be invited, works in all other corridors are
going to be taken up simultaneously under 3 different packages. on
completion, this project enables running of more number of suburban passenger
services, and helps in easing out the current operational constraints being
faced in and around Secunderabad Railway Complex.
In
addition to MMTS phase-II project, M/s RVNL have been entrusted with several other
major Railway infrastructural works on SCR such as Doubling and
Electrification of Vijayawada – Gudivada / Machlipatnam – Bhimavaram / Narsapur –
Nidadavolu, and Tenali – Guntur Sections; and Electrification of Gooty –
Dharmavaram and Wadi - Raichur Sections. The General Manager highlighted
the need to speed up the execution of these works to enhance the capacity of
Railways to meet the demands for more number of train services from the
passengers and industry.
Shri
Sunil Kumar Agarwal, Additional General Manager and Principal heads of the
departments of the Zone were present in this meeting. The Divisional Railway
Managers of Secunderabad, Hyderabad, Vijayawada and Guntakal Divisions also
participated in the deliberations through video conferencing.