Traffic
/ Power Block will be imposed between Bharatnagar and Sanathnagar Stations on
Secunderabad-Wadi section of Secunderabad of SCR during the months of February,
March and April, 2015 for three hours from 12:15 pm to 15:15 pm on the
following dates for facilitating works related to crossing of Metro
Rail over SCR track. The details of trains cancelled / partially cancelled /
regulated due the line block are as follows:-
The
traffic / power block will be imposed on the following dates (Tuesdays
& Saturdays only) in order to minimize the dislocation of passenger
services on the section.
Month
|
Day
|
Dates
|
|||
February-15
|
Tuesday
|
03-02-15
|
24-02-15
|
--
|
--
|
Saturday
|
07-02-15
|
14-02-15
|
21-02-15
|
28-02-15
|
|
March-15
|
Tuesday
|
03-03-15
|
10-03-15
|
17-03-15
|
--
|
Saturday
|
07-03-15
|
14-03-15
|
21-03-15
|
--
|
|
April-15
|
Tuesday
|
07-04-15
|
14-04-15
|
--
|
--
|
1)
Cancellations of Passenger Trains: (on the above mentioned Dates)
(i)T.No.57606
Vikarabad-Kacheguda Passenger
(ii)T.No.57518
Tandur-Hyderabad Passenger
(iii)T.No.57517
Hyderabad-Tandur Passenger
(iv)
T.No.57605 Secunderabad-Vikarabad Passenger.
2)
Cancellation of MMTS Sub-urban Trains:(on the above mentioned Dates)
(i)T.No.47137 Lingampalli-Hyderabad MMTS
(ii)
T.No.47138 Lingampalli-Hyderabad MMTS
(iii)
T.No.47139 Lingampalli-Hyderabad MMTS
(iv) T.No.47189
Lingampalli-Falaknuma MMTS
(v)
T.No.47180 Lingampalli-Falaknuma MMTS
(vi)
T.No.47181 Lingampalli-Falaknuma MMTS
(vii)
T.No.47215 Lingampalli-Falaknuma MMTS
(viii) T.No.47182 Lingampalli-Falaknuma MMTS
(ix) T.No.47183 Lingampalli-Falaknuma MMTS
(x)
T.No.47185 Lingampalli-Falaknuma MMTS
(xi)
T.No.47110 Hyderabad-Lingampalli MMTS
(xii)
T.No.47111 Hyderabad-Lingampalli MMTS
(xiii)
T.No.47112 Hyderabad-Lingampalli MMTS
(xiv)
T.No.47113 Hyderabad-Lingampalli MMTS
(xv)T.No.47115
Falaknuma-Secunderabad MMTS
(xvi)
T.No.47198 Falaknuma – Lingampalli MMTS
(xvii)
T.No.47214 Falaknuma – Lingampalli MMTS
(xviii)T.No.47158
Falaknuma – Lingampalli MMTS
(xix)T.No.47169
Falaknuma – Lingampalli MMTS
(xx)T.No.47160.
Falaknuma – Lingampalli MMTS
3)
Trains Rescheduled/Regulated: ( on the above mentioned Dates)
(1) T.No.12748
Vikarabad-Guntur Palnadu Exp Sch.dep.13.45 hrs will be rescheduled by 45
minutes i.e at 14.30 hrs from Vikarabad.
(2) T.No.18519
Visakhapatnam-Lokmanya Tilak Terminus Express will be regulated
between Kondapalli – Secunderabad for 90 mts on Secunderabad Division.
(3) T.No.12702
Hyderabad-Mumbai Hussain Sagar Express will be regulated between
Hyderabad-Sanathnagar by 10 minutes on Secunderabad Division.
(4) T.No.47184
Lingampalli-Faluknuma MMTS (Sch. Departure. 14.50 hrs) will be regulated
between Lingampalli-Bharatnagar by 9 minutes.
4)
Partial Cancellation of Trains: (on the above mentioned dates)
a)
T.No.47200 Falaknuma -Hyderabad MMTS (Dep. 14.15 hrs) will be partially
cancelled between Secunderabad and Hyderabad.
b)
T.No.12025 Pune-Secunderabad Shatabdi Express will be short terminated at
Lingampalli. on these days, service will be partially cancelled between Lingampalli
and Secunderabad.
5) Partial Cancellation of Secunderabad-Pune
Shatabdi Express
T.No.12026 Secunderabad-Pune Shatabdi Exp. will
start from Lingampalli on Saturdays as per Schedule at 15:15 hrs from
Lingampalli. The days of partial cancellation between Secunderabad and
Lingampalli are as follows:
Month
|
Day
|
Dates
|
|||
February-15
|
Saturday
|
07-02-15
|
14-02-15
|
21-02-15
|
28-02-15
|
March-15
|
Saturday
|
07-03-15
|
14-03-15
|
21-03-15
|
--
|
Speed
restriction of 20, 30 and 50 kmph at the location during the above work will be
imposed as per the requirement.